Here you can see a video from my OOW'12 session, where I'm describing how development time splits for ADF projects. This should give you good idea for planning and estimating ADF project development time:
One of the key things - ADF BC development time always takes less comparing to ADF UI development time. This is not obvious when you are about to start your first ADF project, but is always good to know in advance for proper planning:
2 comments:
Anonymous
said...
Hi Andrejus. Great post. That´s good to see that kind of estimation. When you talk about: 200 complex Oracle Forms = 2 years 2000 average complexity = 3 years, you plan how many developers working on that project? Tks.
2 comments:
Hi Andrejus. Great post.
That´s good to see that kind of estimation.
When you talk about:
200 complex Oracle Forms = 2 years
2000 average complexity = 3 years, you plan how many developers working on that project?
Tks.
Hi,
About 15 developers.
Andrejus